The project scope is now set. We completed value engineering of the preliminary designs and budget, right-sizing the project from four sites to three and…
As of June 2026 – all four project sites now have 10% conceptual site plans developed, reviewed, and on to final project scope settlement.
The Iowa Tribe of Kansas and Nebraska’s energy systems project is nearing final design completion and materials being purchased to prepare for the build.
Work on the RESCO project in April 2026 saw us move into the early engineering and planning phases — leading to a clear picture of…
Efforts have shifted toward detailed cost validation, equipment selection, and confirmation of the remaining project scope.
GS3 completed an Estimate-to-Complete review, updating vendor pricing, labor…
Vendor Selection, Data Collection, and Design Updates
Work this month focused on advancing design coordination, regulatory planning, and early procurement activities across the project sites.
GS3 and RESCO aligned on-site locations and…
August Progress Report: Procurement, Design, and Engagement Steps Forward
In March 2024—Secretary of the Interior Deb Haaland announced $72 million from the Investing in America agenda to help Tribal communities electrify homes. At the…