RESCO Project Update: November 2025

Efforts have shifted toward detailed cost validation, equipment selection, and confirmation of the remaining project scope.

GS3 completed an Estimate-to-Complete review, updating vendor pricing, labor assumptions, and installation schedules across solar, battery storage, EV charging, and backup generation components. 

Battery energy storage system (BESS) selection was finalized, and basis-of-design documentation was advanced for core system elements.

Regulatory coordination continued in parallel. QAPP and crosswalk materials were submitted to EPA for review, BABA waiver approvals were confirmed for manufactured products, and updated site plans were shared with Tribal Historic Preservation and environmental review partners to support final clearances.