The project scope is now set. We completed value engineering of the preliminary designs and budget, right-sizing the project from four sites to three and…
As of June 2026 – all four project sites now have 10% conceptual site plans developed, reviewed, and on to final project scope settlement.
Work on the RESCO project in April 2026 saw us move into the early engineering and planning phases — leading to a clear picture of…
Efforts have shifted toward detailed cost validation, equipment selection, and confirmation of the remaining project scope.
GS3 completed an Estimate-to-Complete review, updating vendor pricing, labor…
Work this month focused on advancing design coordination, regulatory planning, and early procurement activities across the project sites.
GS3 and RESCO aligned on-site locations and…